cost component split @ plant level

chandra_sekhar08
Participant
0 Kudos

Hi gurus,

My client requirement is that.... They have two plants as belows and the stock (FG) has moved from plant 1 to plant 2 after production completion basis.

1. Manufactered Plant

2. Consignment Plant

? can i get cost component split report @ each plant level?or not?

if it is passible can any one help me to achive this requirement.

Thanks in advance,

chandrasekhar.T

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Chandra,

What you are looking for is standard functionality.

jason_shao
Employee
Employee
0 Kudos

Hello Chandra,

Please refer to the transaction CK80_99 (Material - Cost Components) .You can display the cost component split for a single material.

You can also use the report S_ALR_87013047 which analyse/compare material cost component splits.

Best regards,

Jason