HI Guys,

Is it possible to change resource during operation confirmation with changing in process order. It is in general greyed out.

Thanks

Kris

Accepted Solutions (1)

Accepted Solutions (1)

former_member200581
Active Participant
0 Kudos

Hi KRIS,

It can be done thro'  Spro Settings - OPK0 (Single screen entry of Confirmations)

In that You need to select the option 3 - Personnel : Incl. Work centre, wage group......

OR

Please change the workcenter in Production Order itself which copies relevant field parameters in CO11N.

OR

read the PP master data again choosing the relevant production version. you can maintain different routing counters for routing having different work centers. different production version will have different routing counters which inturn will have different work centers.

This will resolve your problem.

Please revert.

Regards,

Amit Kataria

Former Member
0 Kudos

Hi Amit,

Thabnks for your response.

Actually I am searching for the option1. But in the single screen option there is no work center or resource setting. Can you please guide me how to do? Thanks

Krish

Answers (1)

Answers (1)

Former Member
0 Kudos

Yes, It is solved