Actual Start Dates in Campaign

Guys,

We upgraded from 5.0 to CRM 7.0 EHP 1. I noticed that the actual start and end dates for campaigns which were available in CRM 5.0 are no longer available in the Web UI when I try to create a campaign. Any ideas on how to enable this field?

So far I have tried this in the UI config tool

Component: CPGOE_DETAILS

View: OVEFDetails

From the list of available fields, I tired adding these to see if it works..

I tried adding Actual Start and Actual End fields - But these did not show up as date fields on the Web UI

I tired adding Start date & End date - But these are not showing up correctly.

Any Ideas on how to make this work?

Anirudh

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 25, 2012 at 07:42 PM

    This has been resolved. I was picking the Actual start & end from wronger folder. I picked them now from the attributes folder in the UI tool and these fileds are now enabled

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.