Hi All,

After closing the existing MM period through MMPV, system is resetting the previous periods. Client was copied in the month of 10/11.

Eg: Now in MARV - Period for the respective company code is 09/11 and 10/11

After closing this previous periods till 02/12, MARV shows 01/12 and 02/12.

After two days, MARV shows 09/11 and 10/11. It occurs frequently. We are unable to find the reason for resetting the same?

Please let me know your inputs / or Any guess????

by

Prabhu

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Feb 02, 2012 at 01:46 PM

    Hi,

    Once you close a period , it is not possible to reopen the period in the production environment.

    how ever you can have the previous period to get posted.

    does the company code you work with are done with any transactions?

    MARV table by itself will not get changed .

    Does it changed through the config which will be in material master at SPRO ?

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Ragavendra,

      I am also facing the same issue...

      Can you please let me know what are the other config or customizations that may impact this data in MARV.

      In our case the MARV data was changed and the change is also inculded in a TR, and we transported the same TR to quality also.

      Now in quality also the periods were changed.

      What will be the other causes that may affect this data of MARV.

      Thanks in advance,

      Satya

  • author's profile photo Former Member
    Former Member
    Posted on Feb 02, 2012 at 01:35 PM

    Hi ,

    Please Go to MMPV and You will close 11/11 and 12/11 Periods and ofter that You will close the 01/12 and 12/12 periods ofter that you will check the MMRV

    Thanks,

    Raviteja

    Edited by: Ravi Teja.T on Feb 2, 2012 2:35 PM

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Once I have closed the existing periods, it is working fine with the new periods 01/12 and 02/12. But after some period, system is resetting to 09/11 and 10/11. Again we need to do MMPV.

      We are unable to find the reason for this.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.