on 06-20-2011 11:20 AM
Sir / Madam,
I want to make reservation through Maintenance Order.
As per our scenario all material are being considered as project stock
& stocked at different WBS level.
When I am doing reservation through Maintenance Order Component Tab,
reservation getting generated for only one WBS. (This is applicable
only after assigning WBS element in Additional Data tab of Maintenance
Order and selecting "2 = Project Stock" component tab.)
Requirement is that we want to make reservation against different WBS,
through maintenance order.
Please suggest how to do it?
Regards.
Hi,
Assign the WBS in equipment master. Activate the Object list entries to operations in IMG config Define Notification & Order Integration & assign the components for the operations. Then check the same.
I have not tried this. Please check.
Regards,
Maheswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.