Former Member
Jun 20, 2011 at 10:20 AM

Reservation for Maintenance Order against many WBS.

71 Views

Sir / Madam,

I want to make reservation through Maintenance Order.

As per our scenario all material are being considered as project stock

& stocked at different WBS level.

When I am doing reservation through Maintenance Order Component Tab,

reservation getting generated for only one WBS. (This is applicable

only after assigning WBS element in Additional Data tab of Maintenance

Order and selecting "2 = Project Stock" component tab.)

Requirement is that we want to make reservation against different WBS,

through maintenance order.

Please suggest how to do it?

Regards.