Can any one explain me the use of Mixed MRP indicator in MRP view of material master. What is the use of this and when we need to activate this. Thx in advance
in case of strategy 70- maintain Mixed MRP indicator as 1 - Subassembly planning with final assembly
strategy 11 - maintain mixed MRP indicator as 2 - Gross requirements planning
strategy 74 - maintain mixed MRP indicator as 3 - Subassembly planning without final assembly
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Mixed MRP indicator is used mainly in case when Gross Requirement Planning is used i.e. when you have requirement of not considering plant / stor locn stock in MRP run then you need to use strategy group 11 Gross requirement planning along with Mixed MRP Indicator as
2 Gross requirements planning
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.