Not getting Agg. plan POC

Hello Gurus,

I have searched the forum and checked the measures suggested in the various queries (like maintaining stat. key figue / value category / checking consistency etc.), still I could not achieve the result.

The problem is when i execute Progress analysis, using Time proporationality method, Aggregated plan POC is not appearing whereas I get Nagg POC (object wise). I am maintaining POC weight only at the 2nd level of WBS whereas activities are spread among 2nd -4th level of WBS elements. Default method I defined as time proporatioanlity. Also, I maintained for POC Weighting - 6.Weight (Active project) in the config and maintained Basic & Finish dates in WBS element. I am getting Agg.plan POC for Activities whereas not for WBS element. What is that I am missing with which Aggregated Plan for WBS elements can be seen ?

thanks in advance.

Vinodh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 08, 2010 at 06:42 PM

    Hi

    have you run the transaction CNE1 and CNE5.