Assigning calendar to MRP Area

0 Kudos

Hello Experts,

how to assign planning calendar to MRP area? Is it possible?

Thank you very much

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can assign a planning calendar for the MRP area at material level. Open your material in MM02, select your MRP area and you will find the field "planning calendar" under tab MRP2. You can also use the report RMMDDIBE to set the planning calendar for MRP areas of multiple materials.

Regards,

Caetano

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You cannot assign a calendar or a shift to a storage location.

You can assign a shift sequence to your work center, though.

Regards,

Caetano

0 Kudos

Hello,

What if I want to assign calendar to Slocs (various opening hours). Is it also possible to set f.e. opening hours (6am to 6pm) for all the Slocs within particular MRP area?

Thanks

Petr