cancel
Showing results for 
Search instead for 
Did you mean: 

Rolling up processing % of work completion at WBS element Levels

former_member218047
Participant
0 Kudos

Hi Experts,

I am trying to roll up the percentage of work completion from Activity to all the top level WBS elements in a Project. The values are getting rolled up to the immediate WBS element but not to the subsequent top level WBS elements.

Do i need to change any configuration settings ? Kindly shed any light on the above said requirement.

Regards,

Sesha

Accepted Solutions (1)

Accepted Solutions (1)

former_member210872
Participant
0 Kudos

Hi Sesha,

If you can see the mechanism of deriving % of work completion, you will notice, % of work completion will rolled up to the top level of project hierarchy only if unit of measurement is same for work Qty allocated to all the activities. System will unable to calculate % of work completion in case UOM is different.

Hope this will help you.

Please revert in case you need more technical clarification.

Thanks & Regards,

Dnyanesh

former_member218047
Participant
0 Kudos

Thanks Dnyan...working fine.

Answers (3)

Answers (3)

former_member469721
Participant
0 Kudos

@WBS (to consider NWA cost).

Hi ,

Check If you have maintained progress methods is higher level WBS also, in case if you have not try to maintain the same and check for the result.

Check progress profile for EV basis and POC Weighting to know if it matches with your planning.

Regards,

Pradeep

former_member210872
Participant
0 Kudos

Please let me know in case you need more clarification,

former_member210872
Participant
0 Kudos

Hi Sesha,

Its working for me, please have screenshot below.

former_member218047
Participant
0 Kudos

Hi Dnyanesh,

Thank you for the response , kindly let me know how it works ?

Regards,

Sesha