Skip to Content
author's profile photo Former Member
Former Member

upper limits

Hi all

I´m trying to run a SNP optmization, but for the first bucket period stock transfer, purchase requisition and production planned are not allowed

I´m using a time bucket profile of 3 months with 2 months display in weeks. I have a demand of 1000ST for the first bucket (first week) and the tool is suppose to plan production orders for this first period because the stock on hand in this location is bellow the demand (stock on hand < demand)

The tool is showing the followed message:

Production process model PPM_10008_1160 cannot be executed from bucket 20090831->20090906 to bucket 20090831->20090906 because the upper limit for the number of executable lots was set to 0.

How can i fix this in order to SNP optmization start planning production orders, stock transfer and purchase requisition from the first period.

For example: time needed to produce this order is less then 1 day, the planned delivery time to procure is les than 2 days (there are enought stock for the first period to use for the PPM). and the time to transport the good is 8 Hours.

Regards

David

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Sep 04, 2009 at 09:16 AM

    Hi David,

    I hope you are well.

    I guess you checked the production and stock transfer hosrizon in the product master...

    Do you use cross-period lot size planning?

    Could you also try the following: set your planning book to start one week in the past (you can define a lag in the planning book) and try again... Do you have the same result?

    Thanks and Regards

    Julien

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      I tried everything, but still I can´t plan order for the first bucket. I´m not using cross-period lot size or bound profile.

      I set my planning book to start one week in the past, but this does not work. I´m receving the same message in the optimizer log.

      The tool is showing the followed message:

      Production process model PPM_10008_1160 cannot be executed from bucket 20090831->20090906 to bucket 20090831->20090906 because the upper limit for the number of executable lots was set to 0.

      Please someone tell me where can i change the upper limit for the number of executable lots.

      Thanks!!

      David

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.