Planned Order end Date is not re-calculating when the Start date is changed

former_member589292
Discoverer
0 Kudos

Hi PP Experts.

Could you please advise why the planned order end date(Finish date ) is not re-calculating in MD12 , I have In-house production of 3 days in MRP 2 View and sch,.type as Forward and Adjust date based on order start date in OPU5 .

Please advise.

Manojkumar Radhakrishnan

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The planned order dates are generally not adjusted by forward scheduling, as the finish date should represent the requirement/shortage date.

See SAP KBA 1913017 - MRP: Forward scheduling and adjust basic dates

Regards,

Caetano