on 09-20-2018 4:02 AM
Dear Guru's,
I have a situation where user wants to delete dependant requirements and purchase requisitions of raw material as they are no longer in production. The header material of the raw material is not having any demand. Can you please suggest me how to delete the demand for raw material.
Hi
Doesn't sound right. Did you run MRP? Did it raise any exceptions? In case of multi-level BOMs, it could be that you still have firmed planned orders on semi-finished materials which MRP won't touch.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.