How to delete dependant requirements and purchase requisitions

pradeepkumar21
Participant
0 Kudos

Dear Guru's,

I have a situation where user wants to delete dependant requirements and purchase requisitions of raw material as they are no longer in production. The header material of the raw material is not having any demand. Can you please suggest me how to delete the demand for raw material.

Accepted Solutions (0)

Answers (1)

Answers (1)

janbuchmann
Contributor
0 Kudos

Hi

Doesn't sound right. Did you run MRP? Did it raise any exceptions? In case of multi-level BOMs, it could be that you still have firmed planned orders on semi-finished materials which MRP won't touch.