Valuation area not yet productive with material ledger

Former Member

While doing goods receipt at MB1C,i got the below error:

The description of the error is given below

Valuation area XXX2 not yet productive with material ledger

Message no. C+020

Diagnosis

The material ledger has been activated for the valuation area but material data has not yet been converted in this valuation area.

Procedure for System Administration

If you want to work with the material ledger, choose Accounting -> Controlling -> Actual Costing/Material Ledger -> Utilities -> Production Startup.

There you can convert the data for the material ledger by following the instructions in the online documentation.

Note

Setting the material ledger to productive cannot be undone.

See also:

Actual Costing/Material Ledger in the SAP Library.

The implementation guide for Actual Costing/Material Ledger.

Can you kindly suggest me how to fix this error.

Regards

Sabera

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Hi Sabera,

The Valuation Area is not activated for your material ledger. Go to SAP Access>>Accounting>>Controlling>>product cost controlling>>Actual Costing>>environment>>Production Start up>>Set Valuation area as productive.

If you already activated Valution area in to Productive Statge.

Then go to T.Code OMX1 and for your valuation area XXX2 tick the ML activation box.

the error wont come

regards

srikanth

Former Member
0 Kudos

Hi Srikanth,

Thank you for your inputs. I have solved the problem.

Regards

Sabera

0 Kudos

Hi,

I cannot find below path in S4 HANA.

Could you tell me the path in S4 hana?

Go to SAP Access>>Accounting>>Controlling>>product cost controlling>>Actual Costing>>environment>>Production Start up>>Set Valuation area as productive.

Best Regards.

learner_98
Member
0 Kudos

You can use Transaction code CKMSTART

Answers (3)

Answers (3)

former_member870116
Discoverer
0 Kudos

In s4hana it's mandatory to maintain material ledger at valuation area.Go to omx2 you can create your own or Go to omx3 create and assign material ledger which is 9000 is standard one then in omx1 select the activation and pur 2 which is transaction based then Goto ckmstart and execute....or follow thishttps://www.linkedin.com/posts/shobhan-samantray-aa854b25b_sapmm-s4hana-freshers-activity-7031208262939066369-vPjC?utm_source=share&utm_medium=member_android thanks

0 Kudos

choose Accounting -> Controlling -> Product Cost Controlling -> Actual Costing/Material Ledger -> Environment -> Production Startup -> Set Valuation Areas as Productive.

0 Kudos

message no. c+020 r

choose Accounting -> Controlling -> Product Cost Controlling -> Actual Costing/Material Ledger -> Environment -> Production Startup -> Set Valuation Areas as Productive. or background->CKMSTART