on 01-14-2009 1:06 AM
Hi
Can we include an APD in a process chain. If we cannot can we schedule it in such a way that it automatically starts when a particular process chain ends.
Thanks
Rashmi
Yes we can include APD in the process chain. You need to take the process type as ABAP Process
Take the program name as RSAN_PROCESS_EXECUTE
Take the Program variant as --- name of your APD.
Regards,Vj