on 12-10-2008 8:05 AM
While uploading MRP for a material, i am getting error :
The MRP controller 001 does not exist for plant 0570
How to resolve this?
regards,
satyendra singh
Hi:
Check whether you have another MRP Controller created for this plant and and your upload file is having 001 as MRP controller,check if it is and update the file with correct one. And if this is not the case at all,create MRP controller 001 for your plant in customizing:
SPRO > MM>Consumption based planning > Master data> define MRP controllers --> Mention for your plant.
Cheers
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pls maintain the material for that plant in MM01,
sri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
define your MRP controller here:
SPRO >> MM>>Consumption based planning >> Master data>> define MRP controllers >> Here define for your plant..
Hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.