how to link job to task in eclipse ?

former_member256680
Participant
0 Kudos

Hello,

I want to create custom processes to Add privileges in IDM8.0.

I created new process > added Action task from Palette. The next thing, i want to create job (To Database pass ) & map to Task.

I dont find any quick reference to do this? kindly help.

in IDM7.2, i was able to link new Job to task, is it possible in IDM8 as well ?

Accepted Solutions (1)

Accepted Solutions (1)

Chenyang
Contributor
0 Kudos

Hi Imran,

Yes you still can. just need a little bit patience, drag the action task around the straight line, when the line becomes dotted line, then it is added to the process.

Cheers

Chenyang

Answers (1)

Answers (1)

former_member256680
Participant
0 Kudos

Thanks Chenyang,

Yes it requires patience. I am able to create new tasks and add passes to it in eclipse.