MIRO-Import Procurement

Hi,

When i do MIRO for Customs dept. selecting the option as 'planned delivery costs' a dialog box used to be displayed asking for which vendor to be selelected for IV (main vendor / Customs dept).

Now suddenly it is behaving differently. ie it is not giving the dialog box asking for the vendor. and also while i do MIro for main vendor it is not taking the amount and qty from the PO.

anybody any idea?

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 15, 2008 at 06:58 AM

    Please check that you have selected option planned delivery during MIRO

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 20, 2008 at 05:33 AM

    at the time of mogo u r entering the commercial inv no than it is picking the all the values automatcally

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 20, 2008 at 07:02 AM

    hi

    >When i do MIRO for Customs dept. selecting the option as 'planned delivery costs' a dialog box used >to be displayed asking for which vendor to be selelected for IV (main vendor / Customs dept).

    i thinks that the popup will appears when u have multiple vendors in the po for del cost

    like ur customs ,freight vendor ,clearing agent etc

    at this time u will get the popup

    >while i do MIro for main vendor it is not taking the amount and qty from the PO.

    check that u have done gr for the po

    hope it clears

    regards

    kunal

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 22, 2008 at 06:06 AM

    Hi Praveen,

    Pls. do MIRO fist before doing MIGO.

    System will automatically popup the custom vendor & freight vendor, that you need to select adn proceed.

    Pls. ensure that you have maintained custom vendor in the P.O. conditions.

    Pls. award, if found useful.

    Regards

    Rifaie.M

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi

      If you entered different vendors for delivery costs in purchase order and did GR, then you will get that pop up when you choose planned delivery costs.

      Check under conditions in PO if you have entered different vendors, if not change now (provided no GR)

      If GR is done you cannot change delivery vendors in PO, reverse GR and then again do - in GR screen you can change vendors if for the conditions in customization, vendor is GR option 2 is checked.

      In case of GR based IV- if GR is not done, then system will not propose quantity and value automatically. So please check if GR is done or not.

      Regards

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2008 at 07:27 AM

    Hi,

    Check your PO's condition details and change the vendor there.

    I think in condition main vendor is maintained.

    Regards,

    Sachin

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.