Dear PP Experts,

We have some open planned orders from the past which were not converted to a production order. Now through mass processing functions we want to change the start and finish dates of those planned orders in to future dates . Can it be done and please explain how to proceed.

Thanks,

SL

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can do it with CO41 you can use the forward scheduling or past date in backword not allowed with back word scheduling.

So you will get all order in future dates.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Sir,

I checked in CO41 and it allows me to convert planned order to production order and not have any provision to re-scheduling the planned order . Any function to reschedule planned order to future dates ( whose start dates and finish dates are in past ) ?

Thanks,

SL

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

First in OPPQ make the setting start date in paste not alowed. Then run MRP MD02, with planning mode-3 deleted and receated. And check your result.

Or maual scheduling you can do it in MD12 but order wise not in mass by changing the date.

Regards,

R.Brahmankar