Dear PP Experts,
We have some open planned orders from the past which were not converted to a production order. Now through mass processing functions we want to change the start and finish dates of those planned orders in to future dates . Can it be done and please explain how to proceed.
Thanks,
SL
Dear,
You can do it with CO41 you can use the forward scheduling or past date in backword not allowed with back word scheduling.
So you will get all order in future dates.
Regards,
R.Brahmankar