sub conracing in MTO

Hi Fiends,

We are doing jobwok for customes. I have recieved the customer material using mb1c, 501E mvt. type. Maintaind account assignment and item category combination as L-E. now hw to create sub contacting order as system is giving error.please reply...

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Sep 01, 2008 at 11:45 AM

    Hi,

    You want to do material subcontracting,

    In your case u want material to be made at subcontractors end and hence u need to keep special procurement key "30" in material master.

    You also need to maintain a BOM with usage Production

    Info record item category has to be ' 3 '

    PO Item category has to be ' L'

    ME2O is T Code used for sending materials to vendor. M Type to be used is 541

    After completion of job; do GR using MIGO (101 M Type for subcontraced material)

    Check and revert

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 01, 2008 at 11:53 AM

    Hi K ,

    If subcontracting mat is used in FG then include it in BOM . Material master MRP2 set proc type F and sp . key 30 . So that after MRP it will create purchase requi which can be converted to PO .

    Otherwise direct PO can be created in me21n with item cat L .

    On item detail screen click on material tab and check BOM structure or components going to subcontractor .

    For issuing mat use ME2O . Goods receipt is normal ( MIGO ) 103 and 105 if QM is active

    Neal

    Edited by: Neal Gibson on Sep 1, 2008 5:24 PM

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      If u want to create a subcontract PO wrt SO then mention E in the a/c assignment category of PO. U will get a prompt to enter the SO & line item no.

      If u want system to do it automatically by MRP run , then do the setting in material master as follows:

      Prod type F - MRP2 view

      SPK as 30 - MRP2 view

      & 1 in individual and coll. reqmts - MRP4 view

      Now Run MRP, u will get a subcontract PR with SO as a/c assignement.

      Thanks & Regds