MRP correction with planning calendar

317 Views

Hello to everybody,

my need is to adjust MRP calculation based on planning calendar, used in material master. The request is to consider the planning calendar as a sort of vendor calendar.

We want to interact in the MRP procedure as below descripted, for purchase requisition:

1. The standard MRP procedure calculates the PR delivery date and release date based on planned delivery time plus GR processing time.

2. If the material planning calendar includes not working days between release and delivery date, we should add the sum of not working days to planned delivery time.

3. Then the MRP should be executed again to refresh the PR scheduling.