on 08-01-2008 10:24 AM
Hi,
I hv a problem where display a material in MM03, the stock/requirements list is disable. When run in MD04, error date comes after end of valid factory calendar. (Please correct)
I hv corrected the PO delivery date but still the same, wht shld I check now ?
Thanks in advance for anyone reply my question.
extend your factory calendar using transaction SCAL
What you described has probably to do with some field values entered in the material master like delivery days, planning time fence ....
which make the planning determine a date for that you dont have a factory calendar.