Planned order availability check on opening date

Former Member
0 Kudos

Hello All,

I have following requirement, I want to know whether this can be fulfilled in Standard SAP, or by some enhancement:

1. Currently, ATP check in planned order is executed considering the Start date. I want the ATP check should happen considering 'Opening date' instead of Start date.

2. The requirement date in the components are also given on 'Start date' of planned order, I need to shift the requirement date for the components to 'Opening date' instead of Start date.

Kindly let me know how I can fulfill these requirements.

Thanks in advance.

Regards,

Anuj Kaloria

Former Member
0 Kudos

Thanks all. Closing this thread.

Requirement has been fulfilled using lead-time offset.

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

There is a field called "Lead-time offset" on the BOM components. If you set a negative value for this field, the requirement date may be before the order start date, and then the ATP check will be carried out before the start date.


Regards,

Caetano