MRP proposing a very old date as reschedule date

aravind_sankar
Participant
0 Kudos

issue.jpgHi Experts,

I have seen an situation in system that MRP is proposing very old date as reschedule date. Recently i have extended the Planning calendar to Dec 2021 and start date of planning calendar is remain unchanged as 2nd Jan 2012.

After the above change, MRP is proposing rescheduling date as 2nd Jan 2012. Screenshots are attached, Can you please let me know what could be the possible reason and how can we avoid that ?

Note: I am seeing this in MD06. Not seeing this issue in MD04.

Accepted Solutions (0)

Answers (2)

Answers (2)

kumar_semmalai
Contributor
0 Kudos

Hi,

The reason might be , "Start date in the past" setting available in the transaction - OPPR and in-case for planned order, check OPU5.

Regards,

Kumar

JL23
Active Contributor
0 Kudos

see KBA 2500402 - Exception message 15 not displayed in MD04

aravind_sankar
Participant
0 Kudos

Thanks for the KBA Jurgen.

Can you please let me know why system is proposing rescheduling date as planning calendar start date ?

Is there a way can we get an solution on this .?

Thanks in Advance

ASM

JL23
Active Contributor
0 Kudos

see OSS note 25388 - MD01, MD02, MD03: Rescheduling proposals: Documentation