on 02-08-2024 8:26 AM
Within MRP is it possible to mass reschedule PIRs based on a VSF forecast, which have become past due? We would like to reschedule all past due VSFs to a future date x. Subsequently would would review individual demand state & either adjust VSF volume or delete it in all. I'm only aware that we can sweep & delete past due VSFs via MD74.