Can the project status be influenced by billing plan in sales order?

118 Views

I am facing the following problem:

I linked the WBS Element to a sales order billing plan (in header: account assignment).

Now, is there a possibility to prevent changing the status of the project to “close technically”, while there are still some invoices of the billing in the sales order not billed?

I want to make sure that a project can only be closed once all the invoices related to the project were billed.

Thanks in advance