Dear Experts,

Pls tell me is it possible to assigin N number of cost element to one Activity type.

If it is yes ,pls provide the T.code for that.

Thanks in advance

regards

avudaiappan

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Avudaiappan,

You cannot assign N number of Cost Elements to one Particular Activity Type., And Activity type you can create in KL01.

Assign Points if useful.

Regards

P.Ravishankar.

Former Member
0 Kudos

hi,

Thanks for ur immediate reply,

Shall i overwrite in kp26 for the same activity type with other Secondary cost element for cost center planning.

Thanks in advance

Regards

avudaiappan

Former Member
0 Kudos

hi

cannot overwrite the secondery cost element for the activity type in kp26.it already assigned to activity type at creation

Deva

Former Member
0 Kudos

hi,

Thanks for ur reply. I assigned point to u.

Regards

avudaiappan

Former Member
0 Kudos

Hi ,

the txn code is KL01 ( creation ) / KL02 ( Change ) and not KL03 ( only for display ).

Regards

Deepesh S

Former Member
0 Kudos

Hi ,

It is possible to assign a secondary cost element to an activity . The transaction code is KL03 . In the basic data tab you assign the secondary cost element .

Please assign full points

Deepesh S

Former Member
0 Kudos

hi,

My probelm like this

1. i created one activity type, i assigned one secondary cost element , for cost center planning for cost center.

2. now shall i use the same activity type with new secondary cost element for cost center planning for other cost center.

Regards