Summarization levels in COPA assessment

Former Member
0 Kudos

Hi,

During COPA assessment I get a warning message that I haven't defined summarization levels and because of that the performence might be worse.

Is it obligatory to create summarization levels for copa assessment. I only make assessment to product and Company code indexes. The tracing factor is variable COGS.

If i have to define summarization level - how should I do it if only these 2 characteristics are receivers of assessment.

Regards,

Karol

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi.

In customizing (Controlling/ Profitability Analysis/ Tools/Summarization Levels/ Have Proposal Created Automatically) there is a function that helps you to create useful summarization levels. It logs and analyzes the callup of CO-PA transaction and suggest summarization levels that optimize all callups.

Pls assign points if this is helpful.