While using CJ11 I am not able to create elements at level 2.Why? Remedy?
Thanks & Regards,
Seemant
Hi,
CJ11 transaction is specifically for creating a WBS Single element ie you create a WBS element without Project Definition. You should specify only WBS element and Project profile as input. For the WBS element, a project definition will get created automatically in background, provided you have ticked 'Trnsfr to Proj Defn' box in Project profile.
Hence WBS created through this transaction will generally be the <b>only ones</b> in the project and so at level 1.