I made changes to 3KEI table, When i generate transport system is showing up objects in the request. System allows me to change directly in Quality & Development. But how can i transport new changes to Production? Is there any way or program to transport to production.
Its urgent please help.
Thanks
If you have captured the changed made in transaction 3KEI, release the transport request to QA, Check and if happy , move to production.
It does not matter, whether the QA is directly changeable or not. But, in order ensure the QA is test was good, ensure, that the QA is not changed while you are testing. Then move to PRD.