Skip to Content

SAP Net Weaver BPF making parallel activities

Hi im new to sap and trying to make multiple activities inside a BPF to work on parallel, independent from each other by different users.
But the options i got only allow me to make activities that has to be done on order
Is there anyway to make them works independently at the same time?


Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 18, 2017 at 10:50 PM

    The standard only allow you to open the next activity when the previous is complete.

    What I've done in the past was to build an ABAP program to change the activity status to open in the backend, to get all activities open. The only inconvenience was that the program need to be ran every time a new instance was created.

    Add comment
    10|10000 characters needed characters exceeded