I met a problem when carry out the ATP check, when I create the SO for material A 1 pcs and not maintain the storage location in sales order, ATP carried out and gave me the proposal delivery date(100 days later) for about this material, the system can not check the storage location level.

the real situation is for material A, in stock 1000 has 100 pcs, in stock 2000 has 50 pcs, and in stock 3000 has 30 pcs.

How can the system automatic check the storage location level even I not fill in the storage location in the sales order?

Thanks and best regards

Jin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 08, 2007 at 03:20 AM

    Hi Jin

    Probably, in material master, under the tab of MRP2, you would have defined some location in the field "Prod.stor.location".

    Thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 08, 2007 at 04:29 AM

    Jin,

    For this check

    1)Youe storage location shd be automatically determined..Make sure you've done all settings in 0vlk/0vlp..

    2)In MMR-MRP2 make sure you have entered Prod Storage Location..Also in OVZ9 check what stocks you have selected for ATP for particular check rule..

    3)Also in VA02 Go to Environment-Availability overview..

    REWARD IF U FINDS THIS AS HELPFUL..

    Regds

    MM

    Add comment