on 06-27-2007 1:45 PM
Hi Experts,
Is it possible to allow user to input the trading partner (VBUND) in planning of costs in WBS? Meaning, can we add the field "trading partner" in the layout in CJR2?
Thanks!
Many thanks for your replies.
I see the table "COSP" has the trading partner field, but this would only be updated by actual costs (value type = 04,11) or commitment (VT=22), any method that I can update the trading partner to that table with VT=01, planning costs?
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I don't think it is possible to incorporate Trading Partner in Planning Layout. Trading Partner is in Customer Master data / Vendor Master data.
Thanks
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As far as I know it is not possible to incorporate trading partner in CJR2. But I come across this kind of requirement where they have used resource field for trading partner. Means they have created every trading partner as a resource. I am not very sure whether this has worked for them or not.
I am afraid that you may have to go for a custom report
Regards
Siva
User | Count |
---|---|