Dear colleagues,
How to generate a PM order settlement rule to the WBS from that Additional Data tab?
I do not need any WBS for the Location, instead need an hierarchical settlement when order is assigned to the project.
Thanks,
Paulo
Paulo,
User-exit IWO10027 is for this purpose (SMOD).
PeteA