PA transfer Structure & settlement of variances

former_member218048
Active Participant
0 Kudos

Dear All

We are first time using a PA transfer structure in the Production Order settlement profile to settle the variances to CO-PA.

We created the PA transfer structure, assigned the cost elements and value fields.

Then the PA trnsfr structure assigned in the Settlement Profile also.

Now when I try to do the settlement of a Production Order created earlier, it is telling that "Assign a PA transfer Structure".

Why this error even though the PA structure is assigned in the Settlement profile ?

Please help.

Accepted Solutions (0)

Answers (1)

Answers (1)

miya_wang
Active Participant
0 Kudos

Hi,

Please check the cost element mentioned in the error message long text and see if this cost element is included in the PA transfer structure.

Best regards,
Miya