Hi,

Is it required to restart a maintenance plan when we have changed the maintenance package of a task list assigned to that maintenance plan?

Regards,

Nazarene

Accepted Solutions (0)

Answers (5)

Answers (5)

peter_atkin
Active Contributor

Through experience I have always gone to IP10 after changing a strategy based plan to check that the sequence is correct.

Also se this: https://archive.sap.com/discussions/thread/3534724

PeteA

nazarene_madriaga
Participant
0 Kudos

Hi Pete,

Thanks for your reply. My question relates to changing specifically of Maintenance Packages on task list only, not the change of maintenance strategies.

I have simulated to change the maintenance package from a task list, eg. 1000kms to 5000kms within the strategy, but when I try to use IP11U, nothing was selected for an update.

Regards,

Nazarene

former_member696335
Discoverer
0 Kudos

Hi,
Have you resolved you issue ?

peter_atkin
Active Contributor
0 Kudos

Please dont hijack old posts- its against the rules.

.

Instead you should create a new post and refer to any useful information.

nazarene_madriaga
Participant
0 Kudos

To answer your question Mateusz, yes. Had to re-execute IP10/IP30.to resolve it.

peter_atkin
Active Contributor
0 Kudos
nazarene_madriaga
Participant
0 Kudos

Thanks Pete. Have you tried to use IP30H / RISTRA20H? seems to have the description of "Mass Schedule maintenance plans"

peter_atkin
Active Contributor
0 Kudos

I've had a play with IP30H on a previous client, but you'd need to test it for yourself.

PeteA

nazarene_madriaga
Participant
0 Kudos

Can anyone help out in this case if for example you have 900 plans connected to a task list, how do you restart those plans?

psr2412
Contributor
0 Kudos

Take help of ur ABAPer and try with BDC (Batch Data communication) to restart the required Maintenance Plans.

WR,

PS R

nazarene_madriaga
Participant
0 Kudos

Hi PS R,

Have you tried to use IP30H / RISTRA20H? seems to have the description of "Mass Schedule maintenance plans"

psr2412
Contributor
0 Kudos

Hi Nazarene,

Your requirement is to change the start cycle date in Maintenance Plan or it is that you require to reschedule all the Maintenance plans.

WR,

PS R

psr2412
Contributor
0 Kudos

Hi Nazarene,

It is required to start scheduled maintenance plan whenever any changes done in maintenance package of a task list.

Find below link for reference

https://help.sap.com/saphelp_erp60_sp/helpdata/en/c8/10539a639a443ebaedf0f524ed1aed/content.htm

PS R

nazarene_madriaga
Participant
0 Kudos

Were you able to use IP11U when you change packages on task lists?

I don't believe so that will work. it only works when you change maintenance strategies for the maintenance plans.