Change of Maintenance package in Task List

Mar 16, 2017 at 08:02 AM

239

avatar image
Former Member

Hi,

Is it required to restart a maintenance plan when we have changed the maintenance package of a task list assigned to that maintenance plan?

Regards,

Nazarene

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Peter Atkin Mar 16, 2017 at 09:05 AM
0

Through experience I have always gone to IP10 after changing a strategy based plan to check that the sequence is correct.

Also se this: https://archive.sap.com/discussions/thread/3534724

PeteA

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Pete,

Thanks for your reply. My question relates to changing specifically of Maintenance Packages on task list only, not the change of maintenance strategies.

I have simulated to change the maintenance package from a task list, eg. 1000kms to 5000kms within the strategy, but when I try to use IP11U, nothing was selected for an update.

Regards,

Nazarene

0
PS R Mar 24, 2017 at 05:33 AM
0

Hi Nazarene,

It is required to start scheduled maintenance plan whenever any changes done in maintenance package of a task list.

Find below link for reference

https://help.sap.com/saphelp_erp60_sp/helpdata/en/c8/10539a639a443ebaedf0f524ed1aed/content.htm

PS R

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Were you able to use IP11U when you change packages on task lists?

I don't believe so that will work. it only works when you change maintenance strategies for the maintenance plans.

0
avatar image
Former Member Apr 10, 2017 at 01:44 AM
0

Can anyone help out in this case if for example you have 900 plans connected to a task list, how do you restart those plans?

Show 3 Share
10 |10000 characters needed characters left characters exceeded

Take help of ur ABAPer and try with BDC (Batch Data communication) to restart the required Maintenance Plans.

WR,

PS R

0
Former Member

Hi PS R,

Have you tried to use IP30H / RISTRA20H? seems to have the description of "Mass Schedule maintenance plans"

0

Hi Nazarene,

Your requirement is to change the start cycle date in Maintenance Plan or it is that you require to reschedule all the Maintenance plans.

WR,

PS R

0
Peter Atkin Apr 10, 2017 at 11:55 AM
0
Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Thanks Pete. Have you tried to use IP30H / RISTRA20H? seems to have the description of "Mass Schedule maintenance plans"

0

I've had a play with IP30H on a previous client, but you'd need to test it for yourself.

PeteA

0