Our client has a requirement and they expect that to be available for go live too. They have say five 32 ton hydraulic press machine. While confirming order, based on the capacity availability or due to any machine problems,they must have option to choose any one among the 5 machines. So as mentioned in the following SCN link i did ( https://archive.sap.com/discussions/thread/1517816 ). I created 4 work centres packing1, packing2, packing3 and packing. Created a hierarchy with Packing w/c as superior, with no of ind capacities 3. And grouped rest of machines packing 1,2,3 under the w/c packing. In operation details in prodn order,cap req assignment it is still greyed out..am not able to proceed further. So actually is this the right step what i do? or the link which i referred is of different logic and what i do is different??

Kindly help with this,because even i need to show this while giving user training too.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 11, 2017 at 05:57 PM

    Hi Jeffrey,

    You should create multiple individual capacities for the machines instead of multiple work centers. Please follow the steps in the thread you have found.

    best regards,

    Jessica

    Add comment
    10|10000 characters needed characters exceeded