cancel
Showing results for 
Search instead for 
Did you mean: 

Why changing task lists with reference to a change number information is not transferring to PDS?

Akshath
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello,

Query: How do I identify which task list (PDS) has changed with the change number in PDS (APO)?

The scenario is, I have routing master data which is modified using the change number BS_PPDS_CHN1.

later I transferred data from S/4 to the APO (PPDS) system via report PPDS_ERP_CUSLNTRTO_CIF_REPORT.

but the changes which applied are not showing in /SAPAPO/CURTO_SIMU (Display Production Data Structures)

#1: Screenshot of CA61 - History of task list (routing)

# 2: PLKO entry where you find the two entries with respect to the task list.

where I found ZAEHL as counter 0000001 and 0000002

# 3. Transfer the data to APO using report PPDS_ERP_CUSLNTRTO_CIF_REPORT

# 4. Display Production Data Structures (/SAPAPO/CURTO_SIMU)

Note: where you find only one entry, as it's PDS which is linked with the production version.

# 5. Hence, created a new production version for the task list (group counter which has a valid date from 01.10.2022) which has a change number.

# 6. After transferring data to APO, you would find the following details.

Note: you would find two task lists or PDS on the APO side but there is no difference, how do I identify which has applied for changes number at the task list level?

Regards,

Akshath L.T

Accepted Solutions (0)

Answers (0)