Change Work Schedule Rule for a group of employees

0 Kudos

Hello,

I have recently started working on SAP HCM. I have been assigned a task to change the Work Schedule Rule for a group of employees for two different Personnel Areas for a period of 3 months.

After the completion of 3rd month, the old Work Schedule Rule must be applicable. Can you please tell me how I can change the Work Schedule Rule for a group of employees for the particular period?

Thank you in advance.

Regards,

Indu

A_Gamaleldin
Explorer
0 Kudos

Hi Indu,

You can use IT0007 or IT2003 using LSMW to upload data, and check SAP Help it may help.

Regards,

Ahmed Gamaleldin