Internal Order Linking to PM orders

Dear Experts

I need to create an Internal Order and Link it to PM order,

Following are the Steps I need to perform

PM Order Requisition - Create Internal Order

PM Order Requisition - create WBS element

PM Order Requisition - Create Work Order- PM13 (Maintenance Work Order for Projects) PM Order Requisition - Display Purcahse Requisition

PM Order Requisition - Create Purchase order from requisition

PM Order Requisition - Goods Receipt PM Order Requisition - Asset Captilisation

The UAT Test Script Says

Create Internal Order KO01

Create WBS Element CJ01

Create Work Order IW31 -Order type: PM13

Check PR IW33 , ME53N

Create CAPEX PO from PR -ME21N

Goods receipt -MIGO

Asset Capitalization

These is for Testing Purpose.

But my question is

1) How do I link the Internal Orders to the PM orders?

2) Can Anyone suggest me a Business Flow based on their experience to complete the above mentioned Steps?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 22, 2017 at 12:34 PM

    Enter the internal order on the Location tab of the work order in the Settlement Order field.

    This data can then be used to derive the default settlement rules.

    Unfortunately this data has not been added into the IW38/9 reports yet, but could be easily achieved with a small development.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Pete

      Thanks for the suggestion. I have followed your instructions

      I have created an Internal order, then I use the Internal order no. in the Location tab of the PM order and saved it. But the settlement rule in the PM order didn't change. It is displaying the default Settlement receiver.

      Do I need to change it manually or will it change automatically once we enter the Internal order in the Location tab?

      As per my understanding, We are creating the Internal order, so that we can settle the PM order to the Internal order. Correct me, if I am wrong.

  • avatar image
    Former Member
    Mar 01, 2017 at 06:50 AM

    Dear Shiv,

    Can i know why you want to update wbs -for budgeting or settlement

    If for settlement update in equipment same will flow to location tab

    For budgeting maintain in additional tab.

    For flowing wbs automatically from equipment maintain X in configuration

    define transfer of project or investment program.

    Regards

    Anand