Hi All expert,

i need distribute production order's data to mes system when there is any changes to production order.

May u know how to release this?

Accepted Solutions (0)

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Frank

There is a PP subcomponent called PP-MES which deals with the integration of production orders to manufacturing execution systems. There is something called the Data Replication Framework (DRF), which allows you to send master and transaction data to the MES system using IDOCs.

It would be difficult to provide a more detailed explanation here, but you can go through the following link to understand how it works:

https://help.sap.com/viewer/a0d3efbac8b14fc89b29bf47a1677c86/6.17.16/en-US/d383ee6c4b2d4dc59a3dade65...

Regards,
Caetano

ziolkowskib
Active Contributor
0 Kudos

Hi jasonwangcn

I believe you can find the answer in the below article:
Automation of LOIPRO outbound IDOCS.

Regards,
Bartosz

FredericGirod
Active Contributor
0 Kudos

First you need to identify how to connect your SAP system and MES system.

After you could use Change Pointer & job schedulling to process this change pointer.

here an example of change pointer uses with Idoc