Planning calender not working

We have factory calender set up working 7 days and planning calender for 5 days but still planned order/PR are generated on saturday. using standard lot size pk

period looks ok

ppc.png (17.8 kB)
ppc2.png (5.3 kB)
ppc3.png (4.3 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Oct 10, 2019 at 10:19 AM

    Hello,

    Have you assigned the planning calendar to material master?

    You may try an option of 'Do not displace' regenerate period and run MRP again.

    Also Do you have GR processing time in the Material Master?

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 10, 2019 at 01:31 PM

    Hello

    Are you using a Period lot sizing procedure, such as PK?

    Regards,

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 10, 2019 at 03:11 PM

    Do you have a goods receipt processing time for your material? If so, you may have to change the setting "date interpretation" in your lot sizing procedure

    Regards,

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.