Has anyone worked on GATP subcontracting process.
the challenges i see
1. in the component if i gave the batch field, it does not move to SubReq at vendor location in APO (i have subcontracting with source location in APO)
2. As the batch dont move to SubReq... it also dont move to StcTrfRes created as a result for planning run at vendor location
3. Most imp issue: when i do the ATP, i see option to accept the proposed quantities but it actually does not reserve those quantities.
has anyone explored on this? any possible alternative someone used in this case.
Please check the following-
1. Have you activated Vendor and vendor stock Imod?
2. Is Vendor has been CIFed to APO?
3. Is TLANE created in APO for the same?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.