subcontracting process with GATP

Feb 08, 2017 at 11:03 PM

66

avatar image

Has anyone worked on GATP subcontracting process.

the challenges i see

1. in the component if i gave the batch field, it does not move to SubReq at vendor location in APO (i have subcontracting with source location in APO)

2. As the batch dont move to SubReq... it also dont move to StcTrfRes created as a result for planning run at vendor location

3. Most imp issue: when i do the ATP, i see option to accept the proposed quantities but it actually does not reserve those quantities.

has anyone explored on this? any possible alternative someone used in this case.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Mohit Bhagat Feb 17, 2017 at 09:01 AM
1

Please check the following-

1. Have you activated Vendor and vendor stock Imod?

2. Is Vendor has been CIFed to APO?

3. Is TLANE created in APO for the same?