Plan Distribution Run with Fixed Rate as sender rule

Hi

I have created a plan distribution cycle with the sender rule to take as 3-Fixed Rate. After entering that, I have also entered the value in the the sender values & also the SKF value in KP46.

However when I ran the distribution cycle, it does not show any number of receivers, but the receivers are mentioend in the distribution cycle created

Appreciate if you'll could let me know if I select Fixed rate as the sender rule, whether there any other settings that needs to be done and also whether I have followed the correct process

Thanks

Arith

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Jan 13, 2016 at 08:29 AM

    Hi,

    If you select receiver rule as fixed one, need not maintain any planning data in KP46.

    It is required where the option is Variable proportions & Plan SKF's.

    As you have selected Fixed Proportions maintain Fixed amounts / percentages in the segment itself. (Under the tab Receiver Weighting factors.

    Then run the cycle. you will get the results.

    Regards,

    Pavan Kumar Arvapally


    KS.jpg (22.0 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.