Calls are not generating for the scheduling period mentioned

Former Member
0 Kudos

Hi

In Strategy based plan, i created the package  Time based,

Assigned the packages to the operation

Created the maintenance plan strategy based .

On scheduling it is generating one call . I maintained the scheduling period of 60 MON


It is displaying the below message also

All onetime packages for maintenance plan & have been called

Please check the attachment for screeshot

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

rakesh_mane
Active Contributor
0 Kudos

Hello

Please check Maintenance Package Hierarchy .it must have the same hierarchy number

Br

Rakesh

Former Member
0 Kudos

Hi Rakesh,

I  made all Hierarchy no as 1 and created a new plan. Still only one call is generated.

rakesh_mane
Active Contributor
0 Kudos

Hello

Please check have you assigned Each Packages to Task List Operations.?

Also do check Validity Date of Task List should fall after after Maintenance Plan start date.

I am able to replicate your scenario which is working fine please see below settings

Br

Rakesh

Message was edited by: RAKESH MANE

Former Member
0 Kudos

So helpful.  i will try again and let you know. Thanks

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

abraham m,

Run IP13 for your strategy and check that the packages are sequenced/aligned as expected.

PeteA