Hi
In Strategy based plan, i created the package Time based,
Assigned the packages to the operation
Created the maintenance plan strategy based .
On scheduling it is generating one call . I maintained the scheduling period of 60 MON
It is displaying the below message also
Please check the attachment for screeshot
Thanks
Hello
Please check Maintenance Package Hierarchy .it must have the same hierarchy number
Br
Rakesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
abraham m,
Run IP13 for your strategy and check that the packages are sequenced/aligned as expected.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.