Calls are not generating for the scheduling period mentioned

Hi

In Strategy based plan, i created the package  Time based,

Assigned the packages to the operation

Created the maintenance plan strategy based .

On scheduling it is generating one call . I maintained the scheduling period of 60 MON


It is displaying the below message also

All onetime packages for maintenance plan & have been called

Please check the attachment for screeshot

Thanks

strategy.gif (143.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 09, 2015 at 05:46 AM

    Hello

    Please check Maintenance Package Hierarchy .it must have the same hierarchy number

    Br

    Rakesh

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 09, 2015 at 11:04 AM

    abraham m,

    Run IP13 for your strategy and check that the packages are sequenced/aligned as expected.

    PeteA