How to update sto intra plant to plant document flow under the repair order document flow?

Hi Exports,

                My client requirement is , now we configuring the Repair order process that is we have to be created the notification in Tcode IW51 and with reference notification repair order has to be created and delivery with PGR.  After PGR client want to send the unrestricted stock from their plant to repair Site( other Plant) so we can do this via STO Process. But client need that Sto process has to be updated in document flow under  to the Notification/ Repair order document flow. So what can we do for full fill the client requirement.


Thanks In advance if any one clear this requirement.



Regards

Sreekanth

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 05, 2015 at 10:40 AM

    Hi Sreekanth

    If MM and LE transactions are used to carry out the goods receipts there is a customising setting that is used to make sure the document flow of the reference delivery is updated.

    Customising path below.

       -> SPRO
         -> Logistics Execution
           -> Shipping
             -> Basic Shipping Functions
               -> Configure Global Shipping Data
                 -> V_TVSHP-SPE_INB_VL_MM must be ticked.

    Normally on the SD side the purchase order (STO) is updated into the sales document flow in a third party process where the schedule line category generates a reference Purchase requisition, perhaps you could use that process to meet your requirement. Otherwise if it is not updated in standard in the way you need you should be able to write an entry into VBFA when the delivery goods receipted in
    VL* transactions using user exit MV50AFZ1 either form USEREXIT_SAVE_DOCUMENT or USEREXIT_SAVE_DOCUMENT_PREPARE

    I hope it helps you further
    Kind regards
    Brian


    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      to be honest i didn't undestrand exactlly the issue but you can create STO with suppling and receiving plant the same . the storage locations should be different.

      BR.

  • avatar image
    Former Member
    Jan 08, 2015 at 07:02 AM

    Hi Experts,

                          Can any one give correct answer.

    Regards

    Sreekanth

    Add comment
    10|10000 characters needed characters exceeded