Maintenance order cost flow

former_member201392
Active Participant
0 Kudos

Hi...Gurus .....

My client want the maintenance cost as per the process wise, so can you explain  how the cost arriving via the maintenance work order.

i have 3 work centers :- Mechanical, electrical & Tool.

in my Work center i assigned the Cost Center :- Main01 , but in my equipment i assigned the cost center :-  Extrusion-01 (Dept cost Center).

how the cost flows from the order .

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor

Hi,

Cost center in work center will calculate the labour cost and post into the order, activity pricing should be made to include the cost.

Cost from various areas like internal / external materials & Internal / external labour will be settled to the equipment cost center, if the equipment cost center is maintained in settlement rule.

Regards

Terence

former_member201392
Active Participant
0 Kudos

Hii...Maria ...

thanks for sharing the same .

but can you explain me what is use of Cost center which is defined in the Work Center.

because at the time of settlement finally all the cost will be settle on Equipment Cost center.

Please elaborate if possible.

thansk

Former Member
0 Kudos

Hi Lokesh,

If you client wants Process wise cost. You can get it using an Order type. For Example Breakdown Cost, Preventive Cost etc.

If they do not want by Order type, You can use Pm activity type (ILART). For example Mechanical, Electrical etc. (MCI8 Report)

Work Centre Cost: Only to Calculate the cost of activity type (Labor/Machine/Group of people) so that they can be paid accordingly.

Equipment/FL Cost Centre: To calcuate all the cost incurred including activity type cost (WC Cost).

Hope this helps

Thanks and Regards,

Sanjay Tiwari

former_member201392
Active Participant
0 Kudos

Thanks sanjay ....really help full

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Lokesh,

The Internal Labour cost will flow:

The Order will be debited with costs from the Sender (Work Centre) Cost Centre when you plan & confirm labour hours (with an Activity Type & rate in KP26)

The costs will be settled to the Receiver Cost Centre (from technical object such as Equipment) via the Settlement Rule when the Order is settled in CO.

See some useful info:

Cost Flow Of Maintenance Orders