cancel
Showing results for 
Search instead for 
Did you mean: 

How to map Resource related billing through sap pm

Former Member
0 Kudos

Hi all,

I have a new requirement from one of my client.


one plant(says A) provides the maintenance workers to other plant(Says B).


Plant A charge on hourly basis to plant B. Workers fill time sheet daily.


Then how to map this scenario through sap pm.


i guess it should be done through work center. kindly share.

Accepted Solutions (0)

Answers (2)

Answers (2)

peter_atkin
Active Contributor
0 Kudos

punit punit,

There are different options depending on whether the plants are in the same Company Code , or not??

PeteA

Former Member
0 Kudos

kindly share both scenarios. i have requirement in both. for overseas plant in different company code and in same company code.

peter_atkin
Active Contributor
0 Kudos

For scenarios where the plants share the same company code, then you execute and settle your work orders as per normal.

Typically this involves the sending (from work centre) and receiving (settlement) costs centres posting actual costs.

The cost centre managers can then determine how much to back-charge. This task is often performed by the Finance Team.

For scenarios where the plants do not share the same company code, then you have a few options:

  • Resource related billing (see link above)
  • Plant A creates a PR/PO against Plant B. Then plant B creates a Sales Order against Plant A. This can be automated. The PR/PO could be linked to the order directly, or via a contract, or not at all..

PeteA

former_member186385
Active Contributor
0 Kudos

Hi Punit,

Please go through the link below

https://help.sap.com/saphelp_erp60_sp/helpdata/en/f8/56e78ea009504bb584baa5ad3cb648/content.htm?fram...

it is explained very briefly with two difference scenario

please check and revert if you have any specific questions