CKME Manual Price Release Error (C+811)

My Dear Experts....

The process of client is.....

  1. Do cost estimate for the next period (i.e. costing date from as 1st of every next period) and marking using CK40N on every month 28th
  2. On last day of the month, after business hours, they lock all users except the one performing
  3. Open MM periods (ex: now next month i.e. June)
  4. Open FI periods
  5. Do manual release using CKME

The problem happened is majority of the materials got released except few. For those materials system throughs error message C+811 which says price release can't be done as some of the actual postings have been done for the period (you can find the error message in the screen shot).

I tried to find out what are the actual postings happened against the materials for the peirod, but there are no documents posted.

NOTE: This is the 1st month costing run after upgrading to ECC 6 from 4.6C

I have checked different notes like 190707, 454047, 574930, 1492789, 185837, 555176.

Out of the above 555176 (Late price change) is relevant, but when I propose to client, they say we are not late to apply this note (we are in the initial days of the month).

Even 574930 (resetting material ledger status) is also relevant as I find the status of the materials are more than 30 only. But even client is not ready to accept.

The client wants to know why this error coming up when there are no actual postings related to materials happened?

If you have better idea please advice me how to check out the actual postings happened against materials in this case (either any T.codes, tables etc)

Hoping the solution ASAP....

Regards.....

Jose

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jun 03, 2014 at 02:59 AM

    Hi Jose,

    I think you got to the bottom of it yourself.

    Please check

    Seems like notes 555176 and 574930 are the solution.

    Regarding the process of releasing new prices I would suggest using "Dynamic Price Change".

    SPRO -> Controlling -> Product Cost Controlling -> Actual Costing/Material Ledger -> Configure Dynamic Price Changes.

    Regards,

    Szymon


    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 06, 2014 at 07:37 AM

    Hi Szymon,

    Kindly share the CKM3N screenshot with complete drill down. Try to notice the beginning inventory, you may find revaluation of consumption or post closing document. Please revert back.

    Regards

    Mohit Singla

    +91 8800667560

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.