Skip to Content
0
Former Member
Apr 02, 2014 at 07:10 AM

MRP to Prchs req,sch lines for RM stores identification (For Numbers of procees order)

39 Views

Dear all,

Kindly fine below image.

After running MRP

  • It will show the shortage materials
  • It will show,for that shortage materials automatic Purchase requistion
  • It will show if already purchase order raised shortage materials it reflect as schlines.

My customer requirement is for number of planned order or process order how RM stores will identify shoratge materials,if already purchase order raised for shoratge materials,closing stock of materials in stores.

Eg

I.e for 5 process or planned order

After running MRP

  • Total number of purchase req?
  • Total number of Sched line?
  • Total number of closing stock?

These things have to be viewed by store person for number of process order or planned orders.

Kindly pls let me know how to do it.

Regards

Rajasekaran

Attachments

pastedImage_0.png (60.4 kB)