Skip to Content

Double Transfer Requirrement getting generated after Process Ordre Release

Hi All,

We have this critical issue where system is generating two transfer requirements after process order release.

One of the TR is having Zero quantity whereas another is with requirement quantity. Is there any way to avoid this issue?

Business is expecting single TR

double-tr.jpg (21.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 08, 2017 at 04:33 PM

    Hello

    Did you notice when this requirement with zero quantity appeared? Was it when you generated the order, during release or during any mass processing?


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Caetano,

      Same issue i am facing but the 2 TR are created with same quantity for same material but different creation date and planned date In TR

      old TR is not converted to zero quantity

      one TR is created when relaese of production order

      other is created through batch job

      Can i know how the system will allow create another TR if there is already an open TR for Reservation.